June 2005 Upgrade Package
Background – Original Plan
Original AOP Milestone was to add 4 more WRF runs to the HiResWindow slot:
Add to existing two control runs of WRF-ARW (10km/50 level) and WRF-NMM (8km/60 level)
Two pairs of runs added based on a breeding-cycle for each control run making total of 6
There was no room to do this in Q4 2004 because of delays in CCS upgrade availability
Hurricane runs would supercede just these 4 HRW bred-mode runs but not the two controls which would always run